Projects

The False Floor is Removed!

The original floor is now seeing the light of day after almost 60 years! The sloped floor was covered by a false floor in the early 60’s. You can see the original stage (dark mahogany red) emerge above the orchestra pit. 

The Liberty Theatre Facade Projects

Brick Repointing

       Cost: $40,000

       Status: Complete!

       Funding Partners: Oregon State Historic Preservation Office.  Read more.

Mansard Repair

     Cost: $9,728

     Status: Complete!

     Funding Partners: La Grande Urban Renewal.  Read more.

Upper Window Rehabilitation

     Cost: $4,736

     Status: Complete!

     Funding Partners: La Grande Urban Renewal.  Read more.

 Canopy

     Cost: $56,000

Funding Partners: Oregon Community Foundation, Oregon Cultural Trust, Avista Foundation, La Grande Urban Renewal.  Read more.

Blade Sign

     Cost: $50,000

     Status: Complete!

     Funding Partners: La Grande Urban Renewal.  Read more.

Read more.